Fill Dirt Delivered — 25 Truckloads
25 truckloads of fill dirt delivered — must be compacted in lifts with geotechnical testing before slab pour.
25 truckloads of fill dirt delivered — must be compacted in lifts with geotechnical testing before slab pour.
Stem wall cores filled with pumped concrete grout — encases vertical rebar and completes the reinforced foundation wall.
Stem wall inspection passed — block placement, mortar joints, rebar, and bond beams all approved by Orange County.
Under-slab MEP rough-in complete — waste lines, supply runs, and conduit sleeves must be installed before stem wall cores are filled.
4-course CMU stem wall construction begins — raises house above grade for flood protection and termite prevention in Florida.
Foundation footers poured at dawn with two concrete trucks — early morning scheduling critical in Florida’s heat.
Footer reinspection passed — rebar, forms, and dimensions approved, concrete pour now authorized.
First footer inspection found minor deficiencies — corrections made same day, reinspection scheduled next morning.
Electrical bonding inspection passed — 20-foot ground rod bonded to footer rebar creates the structure’s complete grounding system.
Footer trenches excavated and rebar installed — critical: ground rod must be bonded to rebar BEFORE pour for electrical inspection.