Silt Fence Reinstalled
Silt fence failed RDD inspection and required full reinstallation — hire professionals, inspectors have very specific installation requirements.
Silt fence failed RDD inspection and required full reinstallation — hire professionals, inspectors have very specific installation requirements.
Separate irrigation well installed same day as domestic well — reduces domestic demand and saves on drilling mobilization costs.
125-foot domestic water well drilled by WaterWorks — SJRWMD permit required in advance for all well installations.
Land clearing completed — building envelope cleared, graded, and ready for foundation work with all wetland setbacks maintained.
Surveyor stakes exact house corners post-clearing — reference points that guide all foundation work and construction inspections.
Land clearing begins — building envelope cleared to bare dirt with silt fencing installed at all wetland buffer boundaries.
Culvert pipes installed under driveway — circular driveway designs require two culvert crossings, doubling the cost.
Surveyor stakes wetland buffer lines before clearing — highly visible markers prevent accidental buffer violations and fines.
Building permit issued by Orange County — master permit authorizes vertical construction and all trade sub-permits.
Orange County officially records easement vacation — modified boundaries now legally in effect after an 8-month process.