Stem Wall Inspection Passed
Orange County Building Inspector approved the stem wall construction: proper block placement, mortar joints, vertical rebar placement, and horizontal bond beams all verified. Ready for MEP rough-ins and pour.
Orange County Building Inspector approved the stem wall construction: proper block placement, mortar joints, vertical rebar placement, and horizontal bond beams all verified. Ready for MEP rough-ins and pour.
Orange County issues formal Delineation Agreement letter confirming official wetland boundaries — required before NGP application.
Stem wall cores filled with pumped concrete grout — encases vertical rebar and completes the reinforced foundation wall.
Easement vacation application filed with Ranger Drainage District to gain flexibility for house placement and driveway design.
25 truckloads of fill dirt delivered — must be compacted in lifts with geotechnical testing before slab pour.
Final site plan approved after multiple revisions — wetland buffers, stormwater, setbacks, and driveway placement all confirmed.
Comprehensive survey package delivered — boundary, topography, tree locations, and wetland markers in one document.