Orange County Easement Vacation Meeting
Met with Orange County to initiate easement vacation — utility no-objection letters, neighbor notification, and public notice signs all required.
Met with Orange County to initiate easement vacation — utility no-objection letters, neighbor notification, and public notice signs all required.
Ranger Drainage District approves easement vacation — but Orange County approval still required for full legal release.
Easement vacation application filed with Ranger Drainage District to gain flexibility for house placement and driveway design.
NGP consultant engaged — specialist knowledge of Orange County wetland permitting process is essential and worth every dollar.
Official Wetland Determination Certificate issued by Orange County EPD — valid 5 years, required for all NGP applications.
Signed and returned Orange County Delineation Agreement — creating legal foundation for all subsequent environmental permits.
Orange County issues formal Delineation Agreement letter confirming official wetland boundaries — required before NGP application.
First architectural drawings received from DBSS — design incorporates wetland buffers and optimal positioning within buildable envelope.
Architectural contract signed with DBSS for custom 4,878 sq ft CBS home design incorporating wetland buffer setbacks.
Orange County EPD and environmental consultant jointly walk property to verify and agree on official wetland delineation.