Fill Dirt Delivered — 25 Truckloads
25 truckloads of fill dirt delivered — must be compacted in lifts with geotechnical testing before slab pour.
25 truckloads of fill dirt delivered — must be compacted in lifts with geotechnical testing before slab pour.
Stem wall cores filled with pumped concrete grout — encases vertical rebar and completes the reinforced foundation wall.
Stem wall inspection passed — block placement, mortar joints, rebar, and bond beams all approved by Orange County.
4-course CMU stem wall construction begins — raises house above grade for flood protection and termite prevention in Florida.
Foundation footers poured at dawn with two concrete trucks — early morning scheduling critical in Florida’s heat.
Footer reinspection passed — rebar, forms, and dimensions approved, concrete pour now authorized.
First footer inspection found minor deficiencies — corrections made same day, reinspection scheduled next morning.
Footer trenches excavated and rebar installed — critical: ground rod must be bonded to rebar BEFORE pour for electrical inspection.
Land clearing completed — building envelope cleared, graded, and ready for foundation work with all wetland setbacks maintained.
Surveyor stakes exact house corners post-clearing — reference points that guide all foundation work and construction inspections.