Foundation Footer Preparation

Fermin’s crew excavated footer trenches and installed rebar reinforcement per structural engineering plans.

Critical tip: Install the ground rod (20-foot copper rod) AND bond it to the rebar BEFORE the concrete pour — this is a separate electrical inspection that must pass before the footer pour. Do not skip this step or you will have to core drill through cured concrete.